Other Information:

Map of Large Wind Installations in Wisconsin

Table of Commercial Wind Projects in WI

. . . . . . . . . . . . . . . . . . .

For profiles of Wisconsin's wind projects, information on wind siting, wind related studies and tracked payments to local govenments, go to:

Wisconsin Wind Info Center Logo

RENEW's Wind Resource Website

. . . . . . . . . . . . . . . . . . .

Latest Wind Energy News -

North American Windpower

Windpower Monthly

 

Large Wind in Wisconsin

 

2010 Net Production by Wind Generation Installations Owned by Wisconsin Utilities* (Wisconsin Wind Farm Productivity Comparable to Iowa’s)

Utility

Wind Project

State

Capacity
(in MW)

Output
(in MWH)

Capacity factor

WI Public Service Corp.

Crane Creek

IA

  99

271,539

0.3131

WI Power & Light

Cedar Ridge

WI

  67.65

178,005

0.3004

Madison Gas & Electric

Top of Iowa 3

IA

  29.7

  70,415

0.2706

WI Electric Power Co.

Blue Sky Green Field

WI

145.2

326,880

0.2570

*All of the wind projects listed contribute to the utilities’ required supply of renewable energy a specified under 2005 Act 141.

 

 

 

Economic Impacts of Utility-Owned Wind Energy Projects

Wisconsin Projects 

Name/

County/

In-service date

Megawatts/

Wind Turbines

Utility

Total Investment

WI-based construction craft labor (in hours)*

Annual revenue to WI landowners/ local govts.

Blue Sky Green Field

Fond du Lac

May 2008

145/88

We Energies

$305 million

116,600

$1,020,000

Cedar Ridge 

Fond du Lac

Dec. 2008

68/41

Alliant-WP&L

$179 million

54,325

$   477,000

Glacier Hills Columbia

Dec. 2011

162/90

We Energies

~$360 million

119,250

$1,188,000

 

375/219

 

~$844 million

290,175

$2,685,000

 

Out of State Projects  

Name/

State/

In-service date

Megawatts/

Wind Turbines

Utility

Total Investment

WI-based construction craft labor (in hours)

Annual revenue to WI landowners/ local govts.

Top of Iowa 3

Iowa

Feb 2008)

30/18

MGE

$59 million

0

0

Crane Creek

Iowa

Dec. 2009

99/66

WPS

$251 million

0

0

Bent Tree

Minnesota

Jan. 2011

201/122

Alliant-WPL

~$475 million

0

0

 

330/206

 

~$785 million

0

0

 * Assumes 1,325 job-hours per turbine (estimate from Boldt Construction)