Utilities Ramping Up Solar Power Build-Out

Utilities Ramping Up Solar Power Build-Out

But their anticipated output would not be sufficient to serve data center projects in the construction pipeline

*Guest Blog by Michael Vickerman—RENEW Wisconsin Board Member

Construction of large solar power plants in Wisconsin will accelerate throughout the decade, thanks to a series of regulatory approvals handed down over the past 12 months. Indeed, by all appearances, solar power will dominate utility investment in new sources of electric power for the foreseeable future.

In March 2026 alone, the Public Service Commission of Wisconsin (PSC) approved utility requests to acquire three solar projects—two in Columbia County and one in Rock County—totaling 315 megawatts (MW). When energized over the next two years, these three plants will generate more than 600,000 megawatt-hours of zero-emission electricity annually to customers. That amounts to 0.9% of electricity consumption in the Badger State. 

As shown in Table 1 below, WEC Energy and Madison Gas & Electric will add 1.265 gigawatts, or 1,265 MW, of solar power to their generation fleets over the next three years. Construction is well underway at the Koshkonong and High Noon project sites, and ground will be broken this year on the other solar plants listed in the table.

Construction is also proceeding on a 250 MW solar plant in central Wisconsin owned by Minneapolis-based Geronimo Energy. Anticipated to be placed in service later this year, the Portage Solar plant will produce electricity for the wholesale market and sell the renewable energy credits (RECs) from that generation to Microsoft, which will soon complete construction on a hyperscale data center in Racine County. When activated later this year, Microsoft’s facility will become the largest consumer of electricity in the entire state, with a baseline demand of approximately 500 MW. Microsoft will purchase all of the RECs produced by Portage Solar to offset a portion of that facility’s electricity usage. 

Utility-owned solar generating plants often come paired with battery energy storage systems (BESS) placed within the project boundaries. These installations can store up to four hours of electricity at the battery’s rated capacity. 

At the Koshkonong project, for example, the battery system is designed to accept as much as 660 MWh of electricity generated onsite. These BESS units will enable grid operators to discharge stored electricity directly into the transmission system when demand peaks later in the afternoon and evening. 

In just a handful of years, solar has emerged as the fastest-growing in-state source of electric power, and its contribution to electricity supplies now surpasses wind and hydro combined (see Table 2). Accounting for 6.6% of Wisconsin-generated electricity in 2025, solar generation could reach the 10% threshold by 2030.

Will solar growth be large enough to offset anticipated load growth driven by hyperscale data centers? 

As impressive as solar’s growth was in 2025, it wasn’t large enough to fully offset the increase in electricity consumption that occurred that year. The other generation resource that saw a significant increase in output from 2024 was coal, whose rise came at the expense of fossil methane. Factoring in other hyperscale data centers now under construction, it will be a challenge to offset rising electricity sales with new solar generation.

As applied to retail electricity customers, the term “capacity factor” is a measure of their actual electrical consumption in a year divided by its peak demand multiplied by 8,760, the number of hours in a year. The consensus estimate of a hyperscale data center’s capacity factor falls in the 75% to 80% range. 

Compared with other customer types, hyperscale data centers impose an unprecedented level of demand on the electric grids that serve them, due to the following reasons.

  • Massive scale of operations serving millions of users; 
  • Expansion of AI use is driving the need for high-density computing power;
  • Energy-intensive cooling systems; and
  • Always-on operations requiring uninterruptible electrical service.

With the above in mind, let’s estimate the power consumption from Microsoft’s Mt. Pleasant campus that will commence operations later this year. If we assume a peak load of 500 MW and a capacity factor of 75 to 80%, electricity consumption from this particular entity would range from 3.3 to 3.5 million MWh per year, or 5% of the electricity sales recorded in the entire state of Wisconsin last year

It would take six solar plants the size of Koshkonong–1,800 MW in total–to offset, on a MWh by MWh basis, the anticipated consumption from just the Mt. Pleasant data center alone. When the two Beaver Dam and the Port Washington data center projects are brought into the picture, the number of Koshkonong-size projects needed to offset all four hyperscalers in the pipeline would exceed 20. 

Given that, it’s fair to conclude that the data center build-out will elevate greenhouse gas emissions from Wisconsin’s electric power industry even with a robust expansion of in-state solar power. Unless something changes on the ground, this worrisome outcome, and all the unpleasant environmental and economic consequences that it will amplify, is quite literally baked into our future.

Bent Tree North Wind Project Approved

Bent Tree North Wind Project Approved

On April 21, Alliant Energy announced the unanimous approval of the Bent Tree North Wind project. The 153-megawatt (MW) wind project will include 32 wind turbines and expand on the existing Bent Tree Wind Farm, which has been operating successfully since 2011. Since the project is located in Minnesota but will send power to Wisconsin, it required approval in both states.

Upon completion, the Bent Tree North Wind project is expected to generate enough electricity to power about 50,000 homes each year. This expansion of Alliant’s renewable energy portfolio is a win for Wisconsin residents in terms of both energy affordability and grid reliability.

More renewable energy means less reliance on fossil fuels, which at times experience volatile pricing, and diversifies our energy resources. This helps keep energy prices from rising and gives us more options for keeping the lights on.

And while this project will reduce the carbon footprint of our state’s electricity production, it will also be economically beneficial to the region where it is hosted. It is expected that the local area will see $100 million in local economic benefits over the project’s 30‑year (or so) life. Some of these benefits will come in the form of tax revenue, landowner payments, and wages for the 100-150 construction jobs the project will support.

The turbines used for the project will also support the economies in the Midwest. Alliant Plans to use Nordex N133s, a 4.8 MW turbine, which has several key components constructed at Nordex’s Iowa facility.

The turbines are also designed to produce more energy per tower, resulting in less disturbance to the land hosting the project. Standing at an impressively tall 606 feet, the towers are able to support larger rotors, which in turn increases energy production and efficiency. This means more energy at a lower cost.

We’re glad we were able to show our support for a project that fights climate change, boosts local economies, and helps keep Wisconsin’s utility bills more stable. If you want to learn more about this project and some of the other things Alliant Energy has cooking, check out their efforts here—Alliant’s Wind Generation

Energy Storage Utility Aid Law Passes

Energy Storage Utility Aid Law Passes

On April 3, 2026, Governor Tony Evers signed a bill that allows counties and municipalities to receive shared revenue payments when a utility-owned battery energy storage system (BESS) is located within their borders. These payments are referred to as utility aid and will amount to $1,000 per megawatt of storage capacity. Local governments also receive utility aid payments for utility-scale renewable energy projects and energy-producing projects.

Utility aid payments are intended to help local governments offset lost property tax revenue and actually provide more funding to municipalities and counties than the property taxes would have. Property owned by a utility company is tax-exempt.

Beginning in 2027, the bill requires the distribution of utility aid payments to local governments for any energy storage facility with a capacity of at least one megawatt. In order for a BESS to qualify for utility aid, it must be used to store a power source that has been converted from another stored energy source. As an example, solar or wind.

It is becoming increasingly common that utility-scale solar is paired with a BESS. Energy storage adds reliability and flexibility to our energy infrastructure, in part by capturing excess power produced by solar installations in the middle of the day and making it available when needed.

Under existing law, when an energy project is located in a city or village, the municipality receives two-thirds of the utility aid, and the county receives one-third. If the project is located in a town, that allocation is reversed. The same will be true for how utility aid payments from a BESS are distributed.

This law was passed with the support of Wisconsin utilities as well as energy developers that are active in the state. This change is a win for communities that host the energy projects that keep our lights on.

RENEW Wisconsin Supports Bent Tree North Wind Project

RENEW Wisconsin Supports Bent Tree North Wind Project

Wisconsin Power and Light (Alliant Energy) plans to expand its Bent Tree Wind Farm with the Bent Tree North Wind Farm project. Though located in Minnesota, the project will provide power for Alliant Energy customers here in Wisconsin. RENEW Wisconsin is advocating for approval of this project both in Minnesota and here in Wisconsin, as Alliant Energy requires approval from both the Minnesota Public Utilities Commission and the Public Service Commission of Wisconsin.

In its first full year of electricity production, Bent Tree North Wind Farm will produce about 550,000 Megawatt-hours (MWh) of electricity. This is enough to power 55,000 Wisconsin households and reduce emissions produced from energy production by more than 865 million pounds of Carbon Dioxide (CO2) each year. This amount of CO2 would be like taking more than 85,500 vehicles off the road.

Along with CO2 emissions, there are a slew of pollutants that this project will keep out of the air we breathe. As a result, Wisconsin can expect over $1.8 million in economic benefits associated with public health improvements in the first year of Bent Tree North Wind’s operations.

Similar to Wisconsin, Minnesota communities that host utility-scale energy projects benefit from these projects. Bent Tree North will add 150 Megawatts (MW) to the already existing Bent Tree Wind Farm, a 201 MW project. In Minnesota, wind projects are subject to a Wind Energy Production Tax. At about $19,000 per turbine, Bent Tree North will add nearly $650,000 in revenue to be split among Steele, Waseca, and Freeborn Counties. Additional financial benefit will go to the landowners who are leasing their land to make this project possible.

The construction of the project is expected to create 100 to 150 full-time jobs until the project is operational. Additionally, construction workers will contribute to local spending for housing, fuel, meals, and supplies, and construction materials such as concrete and gravel are often sourced locally or regionally.

Though we don’t typically extend our advocacy beyond the borders of our state, this is a great opportunity for both Wisconsin and Minnesota, even if we can’t see eye-to-eye on where Paul Bunyan’s Axe really belongs. Rivalries aside, we look forward to seeing this project approved and will provide an update when we know more!

The PSC Approves Two New Transmission Projects in Wisconsin

The PSC Approves Two New Transmission Projects in Wisconsin

On Thursday, October 30, the Public Service Commission of Wisconsin (PSC) authorized two important transmission projects. These projects are part of the Midcontinent Independent System Operator’s Long Term Transmission Planning (MISO LRTP) processes. They will be jointly owned and operated by Xcel Energy and American Transmission Company (ATC).

The Western Wisconsin Transmission Connection Project (Western Wisconsin Project) will run through the Eau Claire region, connecting Trempealeau County to Clark County. This transmission project will connect with the separate Grid Forward Central Wisconsin Project (Central Wisconsin Project), which will run from the central part of the state to Columbia County. These two projects are a necessary part of the state’s effort to expand renewable energy production in Wisconsin and the broader Midwest region. Updated and new transmission lines support the modernization and decarbonization of the resources that produce energy for Wisconsin’s homes and businesses.

RENEW participated in the legal proceedings for these transmission projects, in which the PSC considered the applications and found that these projects were in the public’s best interest. RENEW’s expert testimony detailed the need for both the Western and Central Wisconsin Projects from the perspective of renewable energy integration and economic development.

According to Xcel Energy, the Western Wisconsin Project alone will “support the full interconnection of over 43,000 megawatts (MWs) of potential new renewable generation in the upper Midwest.”

According to the Wisconsin Zero Carbon Study, Wisconsin will need to rely on an interconnected grid that works with those of neighboring states such as Minnesota, Iowa, and Illinois to integrate renewable energy resources and decarbonize the grid. These two transmission projects will interconnect with another transmission project proposed by Dairyland Power Cooperative, which will be taken up by the PSC later this year. All three of these transmission projects will eventually interconnect with lines in Minnesota. As a result, these projects represent major building blocks for the transmission corridors modeled in the Wisconsin Zero Carbon Study.

As stated by RENEW Policy Director Andrew Kell in his testimony, utility-scale renewable resources will utilize these transmission projects “to support their interconnection and delivery of power to Wisconsin’s homes and businesses. The proposed transmission [projects are key examples] of infrastructure needed for Wisconsin’s clean energy economy.”

RENEW applauds the PSC for authorizing these projects, and we look forward to the many solar, wind, and clean energy storage projects that will be able to deliver clean, reliable energy once these transmission projects are completed.

PSC Approves Badger Hollow Wind, Whitewater Solar

PSC Approves Badger Hollow Wind, Whitewater Solar

On Thursday, September 25, the Public Service Commission of Wisconsin (PSC) approved two utility-scale clean energy projects. Collectively, Badger Hollow Wind (Iowa and Grant Counties) and Whitewater Solar (Jefferson and Walworth Counties) add up to 298 Megawatts (MW) of clean energy!

Badger Hollow Wind

Starting with Badger Hollow Wind—the first 100+ MW project in more than a decade at 118 MW—is a major step forward in Wisconsin’s clean energy future. To meet our net-zero goals, we need to install about 21 Gigawatts of wind energy by 2050.

In taking up the Badger Hollow Wind application, the PSC addressed several issues. In their decision, they considered the requirements of Wisconsin’s wind siting rules and determined that the wind project is in full compliance with sound, shadow flicker, decommissioning, and more.

The PSC also noted public confusion about primary and alternative turbine sites, which are a required part of the process, and limited the wind project to no more than 19 wind turbine sites for the purposes of public clarity. They also applauded the use of an Aircraft Detection Lighting System (ADLS) to reduce blinking lights at night. While the Federal Aviation Administration requires blinking lights to avoid aviation incidents, ADLS will greatly reduce the frequency of blinking, and this will mark the first use of this new technology in Wisconsin!

Expanding the state’s portfolio of wind energy is essential to ensuring we have reliable, clean energy round-the-clock, but that’s not all the project will accomplish. In the testimony RENEW filed with the PSC to support this project, we highlighted several local and statewide benefits.

Benefits of Badger Hollow Wind:

Economic Growth: Badger Hollow Wind will create hundreds of jobs during construction, as well as good-paying, long-term operations and maintenance positions. The project is expected to produce $3.2 million in additional economic activity in Wisconsin.

Community Benefits: Once in service, Badger Hollow Wind will contribute more than $500,000 in utility-aid payments each year. Over $300,000 of this will go to Grant and Iowa Counties, and over $200,000 of this will go to the towns of Clifton, Eden, Linden, Mifflin, and Wingville.

Landowner Engagement: Invenergy has been a good partner to landowners, respecting their property rights and regularly checking in with them to ensure their relationships are positive. Payments to landowners help farmers directly, but Invenergy intends to go the extra mile by building access roads to turbines that farmers can use for their operations.

Whitewater Solar

Whitewater Solar, unlike Badger Hollow Wind, is one of many solar projects to get approved over the last few years, but we’re excited all the same. The 180 MW project takes us another leap forward toward meeting our clean energy goals.

Just as we did with Badger Hollow Wind, RENEW filed testimony with the PSC to show how Whitewater Solar will benefit the state and the communities the project will call home.

During the open meeting, the PSC dove into proposed modifications and conditions to the solar project. Along with standard conditions, the PSC approved additional requirements that address concerns specific to the Whitewater Solar project. In particular, the PSC will require conditions related to the location used for temporary storage of construction equipment, a filing of signed Joint Development Agreements with local governments, and a landowner complaint process to make it easier for the developer to work with local residents before commencing construction.

Benefits of Whitewater Solar:

Economic Growth: Whitewater Solar will create hundreds of jobs during construction, as well as good-paying, long-term operations and maintenance positions. It is expected that this project will produce $259 million in additional economic activity in Wisconsin.

Community Benefits: Once in service, Whitewater Solar will contribute more than $900,000 in utility-aid payments each year. These payments will go to Jefferson and Walworth Counties, the City of Whitewater, and the Towns of Whitewater and LaGrange. Utility-aid payments produce additional revenue for local governments to use to fix roads and support local municipal services, all without creating an additional tax burden for residents.

Collectively, these two projects will reduce emissions by 543,000 tons of CO2 in their first year of operation, which would otherwise come from fossil fuel generators if these projects were never built. This means cleaner air and water, along with mitigating climate change. If you expand that over the lifetime of each of these projects, that would lead to millions of tons of CO2 that we don’t send into our atmosphere. These projects will also lead to reductions in particulate matter and ozone pollution, which means healthier outcomes and reduced healthcare costs for Wisconsin residents. Those who suffer from asthma or have heart conditions are particularly at risk when it comes to air pollution.

Thanks to everyone who helped get these projects across the finish line. Comments from the public, testimony from our partners, and the work on the ground in communities across the state are needed for every project. Through our collective action, we make our clean energy future a reality.