From an article by Lisa Gibson in Biomass magazine:

We Energies has received draft air permits for both the construction and operation of its 50-megawatt cogeneration plant to be co-located at a Domtar Paper mill in Rothschild, Wis.

Following the issuance of the draft permits from the Wisconsin Department of Natural Resources is a 30-day public comment period and hearing, according Brian Manthey, We Energies media relations representative. The public hearing is scheduled for March 1, after which time, the WDNR will make the final decision on the permits. “It should be noted that all of our local permits and variances have passed governmental bodies unanimously,” Manthey said. “We have been pleased by the strong support in the community and we would expect that to continue at the hearing.”